The "Standard" Project Timeline - Once Construction Begins
- Jamie Wallace, CKD
- Mar 24, 2023
- 1 min read
Updated: Mar 27, 2023
When it comes to interior design construction, nothing is standard! But we put together this timeline a general rule of thumb, to help you start planning for your interior design & construction project.
In this blog post, we'll explore the timeline of an average construction project. Each project is unique, and there are always different milestones to achieve. From laying the foundation to adding the finishing touches, each step in the process requires careful attention to detail and expertise.

It's important to trust your project to an experienced team who can navigate these potential roadblocks with ease. Let's take a closer look at the timeline of an average construction project and gain a better understanding of what to expect from start to finish.
Weeks 1-2
Dust & floor protection
Demolition
Straighten & level framing
Sub-contractors rough-in
Plumbing
Electrical
Duct work
Weeks 3-4
Close in inspections
Install insulation
Insulation inspection
Hang and finish drywall
Sand and prime drywall
Weeks 5-6
Painting
Set cabinets
Measure for countertops, need range on site
Install flooring
Countertop fabrication
Weeks 7-8
Interior trim work
Install countertops, if laminate
Subs trim out electric and plumbing
Weeks 9-10
Countertop install, if solid surface or granite
Appliance install
Walk-through and punchlist
Weeks 11-12
Countertop install, if Cambria
Remaining appliance install, if awaiting Cambria
Cleaning, if approved by homeowners
Thank you and photos
Conclusion
No two projects are alike, and yours will almost certainly vary from this schedule. It's also important to keep in mind that all projects are subject to contractor schedules, product deliveries, backorders, accidents, and delays. All the more reason to trust your project to an experienced pro!